The baseline scenario is also a hypothesis

A regulatory impact assessment can get the arithmetic right and still reach the wrong conclusion. It all depends on the future it uses to measure the effect of the new rule.

Dr. Márcio AlcântaraNovember 26, 202613 min read

Imagine a regulatory impact assessment (RIA) that attributes R$40 million in benefits to a new rule in the electricity sector. The estimate looks reasonable, and the calculations are documented. One question is missing: how much of that improvement would happen without the rule?

The answer lies in the baseline scenario. It describes how the problem is expected to evolve if the intervention under review does not exist. To build it, you have to decide what to assume about existing rules, investments already under way, and how companies and consumers will behave. Any of those choices can change the benefit attributed to the measure.

The error of comparing the future with a frozen present

Suppose a problem currently causes losses of R$100 million a year. For a future year, the RIA projects losses of R$60 million with the new measure. In its absence, operational improvements and technologies already being deployed would bring losses down to R$80 million.

SituationAmount in R$ million
Annual losses observed today100
Losses in the future year without the measure80
Losses in the same year with the measure60
Incremental cost of the measure in that year15

Compare today’s losses with the future losses under the measure and the improvement looks like R$40 million. Deduct the R$15 million cost and the net benefit seems to be R$25 million. But the right comparison is between the two scenarios for the same future year: the measure avoids R$20 million in losses, for a net benefit of R$5 million. The earlier calculation credited the rule with R$20 million of improvement that would have happened anyway.

The example is hypothetical and uses comparable monetary values for a single year. When an RIA covers effects over several years, the same logic applies to each period, with future flows discounted where appropriate. If the problem would worsen on its own, freezing the present can produce the opposite error and understate the benefit of taking action.

The UK’s Green Book calls the expected trajectory without the proposal business as usual. It distinguishes outcomes that would happen anyway (deadweight) from those the intervention would add (additionality). The European Commission and Canada’s cost-benefit analysis policy apply the same logic when estimating the incremental impacts of different options. [1–3]

What belongs in a future without the new rule

In Brazil, Article 6 of Decree No. 10,411/2020 requires RIA reports to describe possible options, considering no action, regulatory measures and, whenever possible, non-regulatory measures. It also requires a reasoned comparison of the options. Guidance from Brazil’s presidential chief of staff’s office calls for examining whether the problem would persist, whether it could worsen, and whether the consequences would be irreversible. Anvisa, Brazil’s health regulatory agency, recommends a dynamic baseline that accounts for market developments and technological changes that could alter the problem’s trajectory on their own. [4–6]

The first step is to date the baseline: what rules, contracts and data were available when the assessment was carried out? Next, estimate how things would realistically unfold. A requirement may be phased in, an investment already under contract may depend on permits, and a company may scale back an announced plan if the technology gets more expensive. If an uncertain assumption could change the recommendation, it is useful to calculate the result both if it holds and if it does not.

The options should use the same time horizon, consistent calculation methods and common assumptions about factors such as demand, prices and population. When a measure affects one of these variables, the RIA should explain how. The European Commission also recommends using a common baseline for initiatives developed as a package and explaining what changes if one goes ahead. This helps prevent two measures from claiming the same benefit. [2]

What a smart metering study included in its baseline

In 2024, a study by PSR and Siglasul made available by ANEEL, the Brazilian Electricity Regulatory Agency, compared five models for deploying smart meters in electricity distribution. Option 0 retained the rules in force at the time and incorporated projections from distribution utilities that already planned to replace meters. It also considered cases where utilities reported barriers to expanding their installed base. The projected pace of deployment without the new rule therefore already varied across utilities. [7]

The case changes the question about the benefits of a deployment rule. Some of the meters were already in the utilities’ plans. How much of the change would come from bringing installations forward? How many customer sites would be reached only because of the new measure? And how much of the replacement cost was already planned? The answers may differ across service territories. A national average can obscure both the gains in areas where uptake would otherwise be low and the costs of imposing a schedule where replacements were already planned.

The study’s context shows why timing matters. In January 2026, Brazil’s Ministry of Mines and Energy issued guidelines on additional near-term deployment and on cost-benefit analysis for the medium and long term. A later RIA on the same technology would need to consider the scope of those guidelines and the conditions for implementation as of its own cut-off date. The 2024 version of Option 0 remains useful for understanding the original comparison. [7–8]

When an existing rule is due to expire

Leaving a decision unmade can change the legal landscape. If a temporary rule expires automatically, renewing it with the same wording can produce incremental effects. Australia’s 2026 guidance makes this explicit. When assessing whether to remake an instrument subject to a sunset provision, the baseline is the situation in which the instrument ceases to have effect. [9]

European guidance allows for either expiry or continuation of the policy, depending on the findings of the earlier evaluation and the political commitment to keep the policy in place. When continuation is the baseline, the guidance generally calls for an explicit repeal option. The same European tool allows no action to serve as an analytical benchmark when there is a legal duty to act. In that case, the RIA needs to identify which options are legally available. For a Brazilian reader, the practical question is what happens under the applicable law if no new decision is made. [2]

The assumption that changes the result

Return to the losses in the electricity sector. If projected losses without the new rule are R$70 million, with losses under the rule still at R$60 million and incremental costs still at R$15 million, the net benefit goes from positive R$5 million to negative R$5 million. In this example, the break-even point is R$75 million in losses without the measure. Above that figure, the net benefit is positive. Below it, the net benefit is negative.

This test changes one assumption at a time to show where the conclusion flips. In an actual RIA, it is worth looking at what drives the change. If a drop in the price of a technology speeds up voluntary adoption and also lowers the cost of implementing the rule, both scenarios should be recalculated using the same price assumption. What the reader most needs to know is which plausible combinations of assumptions would reverse the ranking of the options. [2–3]

A UK review shows what this looks like in practice. In the 2026 minimum wage impact assessment, the department used forecast inflation as a proxy for wage growth at the lower end of the distribution, replacing the wage growth forecasts used previously. It cited an expected cooling of the labor market. The Regulatory Policy Committee found the assessment fit for purpose, asked for more evidence to support the change and noted that the study already tested other forecasts. When a recommendation depends on an assumption of this kind, the report should explain why it was adopted and what happens if another is used. [10]

An option can work across more than one future

In strategic foresight, exploratory scenarios describe plausible futures by combining changes in ways that are consistent with one another. The European Commission’s Joint Research Centre used scenarios to test how different policies would fare under different conditions. In Brazil’s electricity sector, the Inovælétrica scenario exercise was one step in developing ANEEL’s five-year strategic innovation plan. [11–12]

One way to apply this approach in an RIA is to compare the options within each plausible future. If technology adoption accelerates, smart meter installation may make substantial progress without the rule under review. If credit becomes more expensive and connectivity is limited, deployment may be slower both with the rule and in its absence. Comparing the two trajectories in each future helps identify when an option remains suitable and when it may be worth phasing in deployment or revisiting the targets.

How to keep the hypothesis open to review

For each assumption that could determine the outcome, readers should be able to find the value or range used, the source and its date, the rationale for the projection, and the effect of revising it. Historical data and signed contracts serve different purposes from statements of intent and expert judgment. When the data cannot support a precise estimate, an evidence-based range or a qualitative description can show what is known and whether it is enough to choose an option. The OECD recommends matching the depth of analysis to the expected impacts and using stakeholder input to test the data and assumptions. [13–14]

In the smart metering case, a consultation could ask distribution utilities for their deployment schedules and the evidence underlying them. Customers and consumer advocacy groups may identify differences in coverage, access or costs that an aggregate projection misses. The final RIA is clearer when it briefly records what evidence led to changes in assumptions and which questions remain open.

Artificial intelligence tools can help with this review by flagging, for example, an investment classified one way in a technical note and another way in a spreadsheet. They can also help prepare tests using ranges supplied by the assessment team. The people responsible for the assessment still need to check the source of each assumption, validate the calculations and explain the judgments that influence the decision.

What a later evaluation can establish

An RIA provides a projection to inform the decision. Once the measure takes effect, the trajectory without it remains hypothetical. If the original projection put losses at R$80 million and the observed figure was R$60 million, the R$20 million difference may reflect both the effect of the rule and changes the projection failed to capture. A simple before-and-after comparison leaves the same question unresolved. Attributing outcomes to the rule requires an appropriate evaluation design. [15–16]

Brazil’s Decree No. 10,411/2020 requires the report to describe how the selected option will be monitored and evaluated. The federal guide to regulatory outcome evaluation, known in Brazil as ARR, recommends planning monitoring during the RIA itself. For smart metering, this could involve recording installation dates, initial conditions, and indicators such as the frequency and duration of outages, with enough detail to track areas where meters were installed at different times. If comparable groups are available, a phased rollout may help estimate effects, provided the evaluation examines earlier trends and why some areas received their meters first. [4, 15–16]

So before accepting the benefit figure in an RIA, return to the question that opened the article. What would happen without the new rule, and what evidence supports that trajectory? A good answer lets the reader reproduce the comparison and see which assumptions would have to change for the regulator to make a different decision.

References

  1. HM TREASURY. The Green Book (2026). London: HM Treasury, 2026. Chapter 4, section Business as usual. Available at: Green Book 2026 on GOV.UK. Accessed on: 26 Nov. 2026.
  2. EUROPEAN COMMISSION. Better Regulation Toolbox. Brussels: European Commission, Dec. 2025. Tools 20 (strategic foresight), 60 (baselines) and 65 (uncertainty and sensitivity analysis). Available at: European Commission toolbox. Accessed on: 26 Nov. 2026.
  3. TREASURY BOARD OF CANADA SECRETARIAT. Policy on Cost-Benefit Analysis. Ottawa, 2018. Sections 5 and 7.5. Available at: Canadian cost-benefit policy. Accessed on: 26 Nov. 2026.
  4. BRAZIL. Decreto nº 10.411, de 30 de junho de 2020 (Decree No. 10,411 of 30 June 2020, on regulatory impact analysis). Article 6, items VI, VII, XI and XII. Available at: updated text at the Chamber of Deputies. Accessed on: 26 Nov. 2026.
  5. BRAZIL. Casa Civil da Presidência da República. Diretrizes gerais e guia orientativo para elaboração de Análise de Impacto Regulatório (AIR). Brasília, 2018. Section 3.2 of the Guide, pp. 38-39. Available at: Casa Civil RIA guide. Accessed on: 26 Nov. 2026.
  6. ANVISA. Guia de Análise de Impacto Regulatório. Guide No. 17/2021, version 4. Brasília: Anvisa, 2022. Section 2.1. Available at: Anvisa RIA guide. Accessed on: 26 Nov. 2026.
  7. PSR; SIGLASUL. Avaliação de modelos regulatórios para implantação de sistemas de medição inteligentes no sistema de distribuição brasileiro. Report R2. Rio de Janeiro, 2024. Annex 003 to ANEEL Request for Input No. 13/2024, PDF pp. 40 and 46. Available at: annex on the ANEEL page. Accessed on: 26 Nov. 2026.
  8. BRAZIL. Ministry of Mines and Energy. Portaria Normativa MME nº 126/2026. Amends Portaria Normativa MME nº 111/2025 and addresses the deployment of smart metering systems. Available at: ordinance on the MME website. Accessed on: 26 Nov. 2026.
  9. AUSTRALIA. Office of Impact Analysis. Australian Government Impact Analysis Framework: practical guide for agencies. Canberra, 2026. Section on sunsetting legislative instruments. Available at: Australian practical guide. Accessed on: 26 Nov. 2026.
  10. UNITED KINGDOM. Regulatory Policy Committee. RPC opinion: The National Minimum Wage (Amendment) Regulations 2026 impact assessment. London, 6 Feb. 2026. Sections Counterfactual and Sensitivity analysis. Available at: RPC opinion on GOV.UK. Accessed on: 26 Nov. 2026.
  11. VESNIC-ALUJEVIC, L.; MUENCH, S.; STÖRMER, E. Reference foresight scenarios: scenarios on the global standing of the EU in 2040. Luxembourg: Joint Research Centre, 2023. Available at: JRC report. Accessed on: 26 Nov. 2026.
  12. ANEEL. Plano Estratégico Quinquenal de Inovação: PEQuI 2024-2028 (five-year strategic innovation plan). Annex to Normative Resolution No. 1,118/2025, item 19. Diário Oficial da União, Brasília, 22 Apr. 2025, p. 43. Available at: Official Gazette page. Accessed on: 26 Nov. 2026.
  13. OECD. OECD Regulatory Policy Outlook 2025. Paris: OECD Publishing, 2025. Chapter 5, Regulating for effectiveness. Available at: chapter 5 on the OECD site. Accessed on: 26 Nov. 2026.
  14. OECD. Regulatory Impact Assessment: OECD best practice principles for regulatory policy. Paris: OECD Publishing, 2020. Available at: OECD publication. Accessed on: 26 Nov. 2026.
  15. GERTLER, P. J. et al. Impact evaluation in practice. 2nd ed. Washington, DC: World Bank; Inter-American Development Bank, 2016. Chapters 3 and 7. Available at: book on the World Bank site. Accessed on: 26 Nov. 2026.
  16. BRAZIL. Ministry of the Economy. Guia orientativo para elaboração de Avaliação de Resultado Regulatório (ARR) (regulatory outcome evaluation guide). Brasília, Feb. 2022. Available at: ARR guide. Accessed on: 26 Nov. 2026.

The opinions and analyses expressed in this article are personal and do not represent the institutional positions, decisions or interpretations of the Brazilian Electricity Regulatory Agency (ANEEL).

How to cite this article

ALCÂNTARA, Márcio. The baseline scenario is also a hypothesis. Regulador.org, 2026. Available at: https://www.regulador.org/en/2026/11/26/baseline-scenario-also-hypothesis/. Accessed on: Nov. 26, 2026.